Reductions by Non-Allocated SMEs Can Enter the Allowance Market Too
Emissions trading is often seen as a big-company scheme. Through external offset projects, however, SME manufacturers that are not allocated entities can turn the greenhouse gas reductions they achieve at their own plants into tradable credits. An external project covers reductions, removals or sequestration achieved at facilities or activities outside an allocated entity's organizational boundary. Once certified, these reductions are converted into offset credits and sold on the market.
The fourth phase of the K-ETS (2026–2030) expands auctioning, so allocated entities have to buy more of their allowances. Demand for offset credits is expected to rise as a result. External projects differ from the voluntary carbon market (VCM) and international mitigation projects we have covered before in three ways:
What the 2026 Approvals Tell Us
According to press reports, the 69th Certification Committee meeting in June approved 20 external projects, including agricultural heat pumps, solar, fuel switching and vegetation restoration. It also certified about 320,000 tonnes of reductions from 13 existing projects. The 71st meeting in September approved 28 projects. These included the first approval of a hydrogen bus replacement project, and two new methodologies were added for SF6 thermal decomposition and distributed combined heat and power.
The methodology list keeps growing, so equipment that does not qualify today may qualify later. The first step is to check whether an approved methodology fits your equipment.
Can Your Equipment Qualify?
Typical project types
Additionality
Every project must demonstrate additionality. Reductions from investments that are legally required, or that you would have made anyway, are unlikely to qualify. Timing also matters. Check the current guidelines to see whether a project must be registered before work starts or whether you can apply within a set period afterward. If you install the equipment first and look into the scheme later, you may lose eligibility.
Admin costs versus scale
Validation and verification involve fees paid to verification bodies. For example, a project that cuts 300 tonnes a year, sold at an assumed KRW 10,000 per tonne, would earn about KRW 3 million a year, and little may be left after costs. For small projects, it is often more practical to consider bundling several sites into one project or working with a project operator.
From Registration to Offset Credits
Combining Government Equipment Subsidies with External Projects
Pre-Launch Checklist and How KITIM Can Help
Always confirm the official methodology list and the latest committee results in notices from the Ministry of Climate, Energy and Environment and the Greenhouse Gas Inventory and Research Center.
KITIM supports the full external project process, from methodology matching, baseline setting and estimates of reductions and revenue to monitoring design, verification support and registration documents. If you are planning an equipment investment, please contact KITIM before you begin. We will help you assess whether your reductions can become a new source of revenue.