From January 8, 2027, Korea's amended Waste Management Act imposes a fine of up to KRW 1 million for late or inadequate entry of waste treatment site data. This guide sets out what SME manufacturers should audit in their Allbaro records and waste contractor management over the three months before it takes effect.

KITIM Consulting Team

What Is Changing — The Core of the Amendment Effective January 8, 2027

The amended Waste Management Act, promulgated on July 7, 2026, takes effect on January 8, 2027. For SME manufacturers, the provision to watch is the one that tightens control over waste treatment data. It creates a new basis for an administrative fine of up to KRW 1 million when waste treatment site data is not entered within the prescribed period or is entered inadequately.

Until now, sanctions focused on failing to enter transfer and receipt records at all, or entering false ones. From next year, late entry and inadequate entry become separate grounds for a fine.

Two layers need to be kept apart.

  • The Act: The fine ceiling (up to KRW 1 million) and the effective date (January 8, 2027) are settled.
  • Enforcement Decree and Rule: Details such as the fine amount per repeated violation were published as draft subordinate legislation, with public comments closing on August 3, 2026. Anything said here about those details is based on the pre-announced draft and should be rechecked against the schedule of the Enforcement Decree once it is promulgated.
  • Who Must Enter the Data — Generators, Transporters and Treatment Operators

    Article 18(3) of the Act requires anyone who generates, collects and transports, recycles or disposes of industrial waste designated by ministerial ordinance to enter the transfer and receipt details and the waste treatment site data into the electronic system (Allbaro) each time. Site data means weighing values, location data and video data.

  • Collection and transport operators: transmit vehicle location (GPS) data
  • Treatment operators: transmit weighing values and video (CCTV) footage taken at the time of weighing
  • Generating sites: enter and confirm transfer and receipt records
  • The site data transmission scheme was phased in for construction waste in October 2022, designated (hazardous) waste in October 2023, and general industrial waste in October 2024. The burden of installing weighing and video equipment and transmitting the data falls mainly on transporters and treatment operators. Even so, the wording of the Act includes generators, so sites that treat or haul their own waste should check the Act and the Enforcement Rule to see whether they are covered by the site data obligation.

    Not being the direct obligor does not remove the risk. A generator must verify a contractor's treatment capacity before outsourcing, and may be subject to a corrective order if the outsourced waste is handled improperly. Repeated delays and errors by a contractor will also diverge from the generator's own transfer records, which is what draws an inspector's attention.

    Where SME Manufacturing Sites Commonly Slip

  • Late entry: records are batched at month-end instead of being entered on the day of removal
  • Weight mismatch: the generator's estimated weight differs from the treatment operator's measured weight
  • Wrong waste codes: confusion over waste oil and cutting fluid, sludge or waste synthetic resin, and misjudging whether a stream is designated waste
  • Staffing gaps: one person covers general affairs, safety and environment, so certificates and accounts are not handed over during leave or after a resignation
  • Paper versus practice: the treatment method or operator in the contract differs from the actual route, or the permit copy on file has expired
  • Designated waste is subject to stricter rules, including treatment plan confirmation and storage time limits, so it is best audited separately from general industrial waste.

    A Three-Month Roadmap Before the Effective Date

    October–November: Audit Your Own Entry History

    Download the past year of Allbaro transfer and receipt records. Compare the gap between removal date and entry date, the difference between generated and treated quantities, and the waste codes. Sort the errors into three types — delay, quantity and classification — and count each.

    November–December: Check Contractors and Tighten Contracts

    Confirm each transporter's and treatment operator's permitted waste types, treatment capacity and the working condition of their site data transmission equipment. Add contract clauses on meeting entry deadlines, notifying errors and allocating responsibility for violations.

    December to the Effective Date: Fix Internal Procedures

    Write same-day entry into the procedure, then designate and train a primary officer and a backup. This is also the point to reflect the finalized fine criteria in the Enforcement Decree.

    Managing It Within ISO 14001 and Compliance Evaluation

    Companies running ISO 14001 do not need a separate workflow. Add the amended provision and its effective date to the legal register, and add "timeliness and accuracy of Allbaro entries" to the compliance evaluation items.

    The resulting records also serve as evidence for customer ESG assessments. Supply chain ESG reviews of waste management mainly ask for proof of lawful treatment, contractor oversight and waste volume data.

    Working with KITIM

    A fine of KRW 1 million is modest in amount. A violation history, however, becomes a record that local government inspections and customer assessments return to repeatedly. KITIM supports environmental compliance diagnostics, ISO 14001 implementation and maintenance, and supply chain ESG assessment response together. If you would like to review your waste management system before the amendment takes effect, please reach out through KITIM's consultation request.

    Waste Management ActIndustrial WasteAllbaro SystemWaste Compliance FinesOutsourced Waste TreatmentEnvironmental ComplianceSME Manufacturers
    매일 자동 업데이트

    이 분야 정부지원사업, AI가 찾아드립니다

    3분 기업진단만 완료하면 귀사에 맞는 공고를 적합도 점수와 함께 추천합니다. 무료입니다.

    AI 맞춤 공고 무료로 받기

    Need Consulting?

    Our technology innovation consultants will propose the optimal solution for your company.